99 MW CONFIRMED
Southern California Edison (SCE) has confirmed that there are no system-wide upgrades required and they can support a total of 99 MW by 2029.
SCE will create approximately 0.5 miles of transmission corridor linking the SCE Inyokern Substation to a planned on-site customer substation. Once constructed, the on-site substation will step down the incoming 115 kV transmission feed, delivering usable medium-voltage power to support full data center operations.
Method of Service (MOS) Issued
Zero Grid Upgrades Required
99 MW in 2029