99 MW CONFIRMED
Southern California Edison (SCE) has confirmed that there are no system-wide upgrades required and they can support a total of 99 MW by 2029. An additional Method of Service (MOS) is expected to be issued within the next four months, delivering an extra 99 MW to the site by 2030-2031.
SCE will create approximately 0.5 miles of transmission corridor linking the SCE Inyokern Substation to a planned on-site customer substation. Once constructed, the on-site substation will step down the incoming 115 kV transmission feed, delivering usable medium-voltage power to support full data center operations.
Method of Service (MOS) Issued
Zero Grid Upgrades Required
99 MW in 2029
198 MW Total in 2030-2031